RAPC Open Requests For Qualifications

(Please see all documents below for each project.  Q&A documents will be added as necessary for each project as firms submit questions per the public notices)

 

 

 

EPA Brownfields Environmental Assessment

 

Metropolitan Transportation Plan

 

Regional Transit Provider/Authority Feasibility Study and Implementation Plan

 

Metropolitan Planning Area Stormwater Study

 

 

 

 

 

 

 

 

 

 

 

Q:   Is it acceptable to add color or shade the lines of the MPO Standard Submittal Form?

 

A: Yes.

 

 

 

 

 

Q:   The Minimum Personnel Requirements we need to designate for No. 12 on the form were not provided in the advertisement. As an example, should we be providing staff such as:

  • a. At least one (1) principal of the prime consultant shall be a professional engineer registered in the state of Louisiana.
  • b. At least one (1) principal or other responsible member of the prime consultant, shall be a professional engineer, registered in the state of Louisiana and shall have a minimum of five (5) years of experience in responsible charge of hydrologic and/or hydraulic engineering.
  • c. At least one (1) professional land surveyor, registered in the state of Louisiana, with a minimum of five (5) years of experience.
  • d. At least one (1) individual or individuals shall have a minimum of five (5) years of experience for Discovery.

 

 

A:  MPR’s were not included in the advertisement; however, as part of Q&A, minimum requirements shall be as follows:

  1. At least one (1) member of the consultant team shall be a professional engineer registered in the State of Louisiana.
  2. At least one (1) member of the consultant team shall have a minimum of five (5) years of experience in responsible charge of hydrologic and/or hydraulic engineering.
  3. At least one (1) member of the consultant team shall be a professional land surveyor registered in the State of Louisiana with a minimum of five (5) years of experience.

 

 

 

 

 

Q: Minimum Personnel Requirements specified under Item No.12 on the MPO form were not provided in the advertisement. Are there any for this project? If not - how should we fill in the table for Item No.12?

 

 

A: Although we did not specify MPR’s in the advertisement, respondents must demonstrate their project team has expertise commensurate to the specified scope of work. Please list team members who will be working on this project in the table.

 

 

 

 

 

Q:          Concerning preparation of the MPO Standard Form does sub-consultant(s) prepare their own form, which is then attached to prime’s MPO Form?

 

A:           Yes.  The prime and the sub should fill out the whole form, but the sub has the option for several questions to state “see Prime’s MPO Standard Submittal Form” if the information would be redundant.

 

 

 

 

 

 

 

 

 

 

Questions and Answers

Rapides Area Planning Commission

803 Johnston Street

Alexandria, Louisiana 71301